Authors: Ashley Rasmussen, Glenn Barr, Rachel Jansen, Nicole Hoffmann
Presented at: Tailings and Mine Waste 2026
Paper Abstract
Designing a responsible and economic tailings storage facility requires confidence in tailings variability and knowledge of how this variability will impact tailings management. Obtaining answers to
key tailings-related questions early in study phases with a tailings test work component during the geometallurgical mapping stage can support critical design decisions.
Geo-metallurgical mapping is a common practice to inform processing plant design and operation decisions based on the variability of the ore to be processed. The mapping process starts with the costly collection of drill core samples, followed by a series of laboratory tests, analyses, and modelling. The “waste stream” generated from the tests (laboratory produced tailings) are a valuable resource that can be used to characterize the variability of the anticipated tailings at minimal additional cost.
This paper presents an add-on approach to any geo-metallurgical mapping program where the laboratory generated tailings are subjected to an additional series of brief indicative tailings characterization laboratory tests. Identifying the tailings variability in terms of dewatering, transport, geotechnical or geochemical aspects can highlight root causes for potential future tailings challenges. This adds significant value to the tailings design with minimal additional cost so that owners can implement an informed and optimized tailings management plan from project initiation. The Twin Metals filtered tailings project is presented as an example to share tailings mapping testing protocols, results, and lessons learned to better future endeavors where this practice may be applicable.