Mineral Processing

Our team of process engineers has a demonstrable history of successfully delivering cost-effective and high-performance mineral processing solutions globally.

With declining feed grades, and increasingly challenging and problematic ores being processed, the modern process plant needs to adapt. Often this means adopting newer and novel technology or modifying and optimising the process flowsheet.

At the early stages of a project we can assist with conceptual studies, planning, process modelling, flow sheet development and debottlenecking studies. From there we develop the design through to detailed design, construction support, and commissioning. This is backed by in-house laboratory testing ranging from specific unit processes up to full metallurgical test programs and pilot scale plants.

For existing plants, we offer a range of services to solve problems and improve operations, including site audits, process and equipment optimisation and upgrades, control development and operator training. This includes the services of registered Qualified Persons for specific requirements.

NOTABLE PROJECTS

Mineral Processing Projects from around the world

Resin-in-Leach to Carbon-in-Leach Conversion Project, Nevada

Ore type changes at this plant necessitated the conversion of an existing resin-in-leach gold recovery process to a carbon-in-leach process. We carried out detailed engineering design which included making the necessary modifications to the existing leach circuit equipment, rerouting the tailings disposal and reclaim water circuits, installing new reagent addition and CN destruction circuits, and adding the ancillary equipment required to support the amended flowsheet.

Fluorspar Grinding and Flotation Optimisation, Mexico

The industrial mineral concentrator has historically suffered sub-optimal flotation performance at two parallel processing plants. We optimised the grinding and flotation circuits to reduce overgrinding and the associated grinding costs, increase overall recovery, and minimise product loss to tailings. The new process flow incorporated a coarsened grind by moving from primary and secondary grinding to a primary grind and concentrate re-grind configuration. We reconfigured flotation tailing recycle streams to improve gangue liberation and maintain concentrate grade while increasing recovery.

Plant Expansion Project, Argentina

Yamana’s Cerro Moro processing facility wanted to investigate which upgrades were required to roughly double the plant’s capacity while processing lower grade ore. Through data analysis, test work review, and process modelling, we successfully completed a conceptual study identifying low-cost options for plant expansion.

Yamana subsequently engaged us to conduct a PFS level study and necessary preliminary work including design and management of the metallurgical test campaign, audit of existing plant circuits, and trade off studies evaluating expansion approach and optimal throughput target required to support PFS engineering.

Corporate Technical Support, Brazil

Yamana Gold’s Jacobina processing facility was undertaking detailed engineering with another engineering firm to allow an increased plant capacity and engaged us to conduct a review of the proposed design of the comminution circuit. In our review of design parameters and operational data, it was determined that many of the expansion targets could be satisfied with existing equipment.

Yamana then engaged us to conduct an audit to confirm the review findings and to manage the expansion by heading a steering committee responsible for overseeing the project to ensure achievement of the site’s low-capital expansion goals. Through auditing and debottlenecking efforts, we have helped the site team to increase from roughly 7500 tpd to 9000 tpd.

Copper Smelter Off-Gas Dust, Dry Handling to Wet Handling Conversion, Southern Africa

The off-gas dry handling system at this smelter was a bottleneck that resulted in substantial downtime due to maintenance and shutting the furnace before the dust could be removed manually from the collection drop box.

We were tasked with converting the dry handling process to a continuous wet handling system by developing a circuit to deal with the dust as well as to do proof-of-concept tests to produce a pelletised product. The process test work included open channel flow, vibrating screens, thickening, pelletising, bulk flow properties, and drying circuit tests and provided the basis for the wet handling system.

For more information, please view our brochures below